30 August 2021

Dublin Port Temporary Traffic Management Plans – 30th August – 13th September 2021

As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 30th August – 13th September 2021

Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:

 

DUBLIN PORT WORKS KEY PLAN – 30th August – 13th September 2021

 

Promenade Road:

Footpath narrowing

Hoarding Placement.

03/03/21 – 15/10/21

   

 

 

  Promenade Road:

Temporary Footpath & Lane 1 Closure for Telehandler Access

01/09/21 – 03/09/21 

       
Terminal Road:

Terminal Rd /
Alexandra Rd

Extension Road
reconstruction works.

 

14/06/21 – 15/10/21

       
  Alexandra Road:  STOP/GO for works to new bridge 30/08/21 – 01/09/21
       
Branch Rd South Single Lane Closure 30/08/21 – 04/09/21
       
 

Bond Drive

Extension:

Bond Drive
Extension

Construction
Access

29/06/21 – 15/10/21  
       

 

 

 

In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858

Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:

Email: info@dublinport.ie

Phone: 01 8876000

We thank you for your co-operation and patience and apologise for any convenience these works may cause.

 

 

You also might be interested in:

DUBLIN PORT DIGITAL ARCHIVE

Go back in time with Dublin Port

 

ANNUAL REPORT

Stay up to date with our year on year growth

 

YEARBOOK

Take a look back on the years events at Dublin Port