Dublin Port Temporary Traffic Management Plans – 23rd August – 10th September 2021
As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 23rd August – 10th September 2021.
Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:
DUBLIN PORT WORKS KEY PLAN – 23rd August – 10th September 2021
Promenade Road: |
Footpath narrowing Hoarding Placement. |
03/03/21 – 10/09/21 |
|
Terminal Road: |
Terminal Rd / Extension Road |
14/06/21 – 10/09/21 |
|
Alexandra Road: | STOP/GO for works to new bridge | 23/08/21 – 27/08/21 | |
Alexandra Road: | Weekend Road Closure for works to new bridge | 27/08/21 – 29/08/21 | |
Evening Temporary Lane | Closure for removal of Standalone Camera | 25/08/21 | |
Branch Rd | South Single Lane Closure | 30/08/21 – 04/09/21 | |
Bond Drive Extension: |
Bond Drive Construction |
29/06/21 – 10/09/21 | |
|
In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858
Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:
Email: info@dublinport.ie
Phone: 01 8876000
We thank you for your co-operation and patience and apologise for any convenience these works may cause.