19 April 2021

Dublin Port Temporary Traffic Management Plans – 19th April to 3rd May 2021

As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 19th of April to 3rd of May 2021.

Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:

 

DUBLIN PORT WORKS KEY PLAN – Weeks 19th April to 3rd May 2021

 

Promenade Road:

Kilwex continues works. Diversion in place for the duration of road reconstruction works.

 

Footpath narrowing, hoarding in place.

08/02/21 – 30/04/21  

 

 

03/03/21 – 16/06/21

       
Terminal Road:

 

Green Tanks Construction Entrance.

 

 

Off peak lane closures for slit trenches inbound.

 

15/11/20 – 30/06/21

 

 

26/04/21 – 06/05/21 

 

       
No.2 Branch Road South: 

Road repairs and line marking.

  15/02/21 – 30/04/21 
       
   Bond Drive:  Lane closures for works to pedestrian crossing.  12/04/21 – 20/04/21 
       
       
       

 

Additional Info: Kilwex will complete works to the pedestrian crossings at Bond Drive this week. Trial Pits and Cabling at Poolbeg Yacht & Boat Club 19th to 30th of April.

In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858

Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:

Email: info@dublinport.ie

Phone: 01 8876000

We thank you for your co-operation and patience and apologise for any convenience these works may cause.

 

 

You also might be interested in:

DUBLIN PORT DIGITAL ARCHIVE

Go back in time with Dublin Port

 

ANNUAL REPORT

Stay up to date with our year on year growth

 

YEARBOOK

Take a look back on the years events at Dublin Port