19 January 2021

Dublin Port Temporary Traffic Management Plans – 18th January to 1st of February 2021

As part of the continuous improvements to the Dublin Port Roads Network, there are several road works taking place across the Port estate between the 18th of January to 1st of February 2021.

Please see below location plan for the affected areas, a brief description of works, and anticipated duration.  All routes will be clearly signposted and VMS boards in place to assist:

 

DUBLIN PORT WORKS KEY PLAN – Weeks 18th January to 1st of February 2021

 

Alexandra Road: TMA Single lane closure for road reconstruction works. 08/12/20 – 07/02/21  
       
Terminal Road: Roadbridge continues work at the replacement Green Tanks Construction Entrance. 09/11/20 – 01/05/21    
       
No.2 Branch Road South: 

Surfacing work taking place in T4 South late this week and into next, with asphalt deliveries through No2 Branch Rd South. Spotters will be in place at the conveyor and gatemen at the entrance to the works, adjacent to Berth 29.

21-22-25/01/21 
       
       
       
       
       

 

 

In addition to the elements shown, Kilwex continue works on Promenade Rd, East of New Customs House, in early February this section will open down as far as the Fairplay Energy Exit.

In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858

Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:

Email: info@dublinport.ie

Phone: 01 8876000

We thank you for your co-operation and patience and apologise for any convenience these works may cause.

 

 

You also might be interested in:

DUBLIN PORT DIGITAL ARCHIVE

Go back in time with Dublin Port

 

ANNUAL REPORT

Stay up to date with our year on year growth

 

YEARBOOK

Take a look back on the years events at Dublin Port