Temporary Traffic Management Plan – 29 August to 5 September 2022

Temporary Traffic Management Plan –  29 August to 5 September 2022

29 August 2022

As part of the continuous improvements to the Dublin Port Roads Network, the following are works taking place across the Port estate between 29 August to 5 September 2022.

Please see below location plan for the affected areas, a brief description of works, and anticipated duration. All routes will be clearly signposted and VMS boards in place to assist:

 

 

DUBLIN PORT WORKS KEY PLAN – 29 August to 5 September 2022

Terminal 7 Entrance

No. 2 Branch Rd North Extension

Monday 29/08 from 7am to Thursday 01/09 at 9am

       

Terminal 7 Alt. Entrance 

Tolka Quay Road

Monday 29/08 from 7am to Thursday 01/09 at 9am
       
 

In case of emergency while traveling on any of these routes – please remain with your vehicle and contact Harbour Police / Port Security: 01 8876858

Should you have any queries in relation to the Dublin Port Roads Network upgrade works please do not hesitate to contact us:

Email: info@dublinport.ie

Phone: 01 8876000

We thank you for your co-operation and patience and apologise for any convenience these works may cause.